Work commences on the new extension,
to provide toilet facilities
at St John Church .




The construction work commenced on Monday 4th February 2019
John Younger of Sudbury, Contractors

April 7th:- Roof Purlins being erected

April 10th:- Church inner door exposed,
this will be the entrance into the new extension
April 11th
Previous door now removed, exposing the original concrete frame.
The breeze blocks are the external wall of the extension

Photographs courtesy of John Cowlin